New secondary suite basement
226 HUNTINGTON CL NE · HUNTINGTON HILLS
Approach the applicant or project team about specification and preconstruction needs.
Development approval can precede detailed permits and trade procurement.
Verify the latest status with the official source or project team before acting.
Project location
Mapped from the public-record address when this page loads. Confirm the official record before visiting.
Why this matters
Development approval can move a project toward detailed design and building permits.
Evidence behind the ranking
- Project is still early enough for preconstruction follow-up
- New or changed public record this week
- 3 related public records linked to this project
- Applicant identified in a public record
Relevant trades
The source describes an interior alteration or renovation.
Medium confidence · Now to approximately 2 monthsInterior alterations commonly require electrical scope.
Low confidence · Now to approximately 2 monthsInterior alterations may require mechanical changes.
Low confidence · Now to approximately 2 monthsThe public description indicates new-build, addition, or structural scope.
Medium confidence · Now to approximately 3 monthsNew-build or multi-unit scope commonly includes plumbing work.
Low confidence · Now to approximately 3 monthsProject timeline
-
Building permit field changed
Status: issued → completed · 1 more field changed
First detected Oct 22, 2026 Official record ↗ -
Construction Brief assessment
Project assessed as general activity at development approved
First detected Sep 3, 2026 Underlying source ↗ -
Development permit released
Development permit released: NEW: SECONDARY SUITE (BASEMENT)
First detected Aug 30, 2026 Official record ↗ -
Development decision
Development decision: NEW: SECONDARY SUITE (BASEMENT)
First detected Aug 30, 2026 Official record ↗ -
Building permit issued
Building permit issued: Improvements
First detected Aug 18, 2026 Official record ↗ -
Development application
Development application: NEW: SECONDARY SUITE (BASEMENT)
First detected Aug 10, 2026 Official record ↗ -
Building permit issued
Building permit issued: Improvements
First detected Jul 29, 2026 Official record ↗ -
Building permit application
Building permit application: Improvements
First detected Jul 29, 2026 Official record ↗ -
Building permit application
Building permit application: Secondary Suite
First detected Jul 29, 2026 Official record ↗ -
Building permit application
Building permit application: Garage
First detected Jul 29, 2026 Official record ↗ -
Building permit application
Building permit application: Improvements
First detected Jul 29, 2026 Official record ↗
Related public records
| Source | Record | Record date | Retrieved | Evidence |
|---|---|---|---|---|
| City of CalgaryCalgary Building Permits | Building permit field changedBP2026-12604 | Oct 21, 2026 | Oct 22, 2026 | Official source ↗ |
| City of CalgaryCalgary Development Permits | development_permit · record_updatedDP2026-04339 | Sep 3, 2026 | Sep 4, 2026 | Official source ↗ |
| City of CalgaryCalgary Building Permits | building_permit · record_updatedBP2026-13623 | Aug 20, 2026 | Aug 21, 2026 | Official source ↗ |
| City of CalgaryCalgary Building Permits | building_permit · record_updatedBP2026-12607 | Aug 20, 2026 | Aug 21, 2026 | Official source ↗ |
| City of CalgaryCalgary Building Permits | building_permit · record_updatedBP2026-12602 | Jul 30, 2026 | Aug 1, 2026 | Official source ↗ |
Want this Calgary feed by trade and value each morning?
Report an error
Submit supporting detail privately. Contact information is not displayed publicly.